Murmansk Oblast - Overview of the project and EIA stages

Contact information for the responsible authorities/organizations in the Murmansk Region. 

Project and EIA stages

Responsible authorities/organizations

Requirement documentation

Step 1. Notification, Declaration of intent, Preliminary Terms of Reference

Notification, Declaration of intent

•  The Ministry of Natural Resources and Ecology of Murmansk region

•  The office of the Federal Nature Management supervision service (Rosprirodnadzor) in the Murmansk region

• Notification

• Declaration of intent

Land Selection Act

 

Municipalities of the Murmansk region

 

• Statement

• Declaration of intent

Preliminary Terms of Reference

 

Project organizations

 

• Preliminary Terms of Reference

 

Public informing and consultations

Municipalities of the Murmansk region

• Statement

• Notification

• Preliminary Terms of Reference

Step 2. EIA investigations and preliminary EIA materials

EIA investigations

Developer or project organization/consultancy

• Preliminary EIA materials

Public hearings

Municipalities of the Murmansk region

• Statement

• Notification

• Preliminary EIA materials

Step 3. Final project documentation

Approval of the project documentation

Governmental authorities

 

Step 4. State ecological expertize and State expertize

State ecological expertize

•  The Ministry of Natural Resources and Ecology of Murmansk region

•  The office of the Federal Nature Management supervision service (Rosprirodnadzor) on the Murmansk region

• Statement

• EIA materials

• Public hearings report

• The results of the Public ecological expertize

State expertize

The regional autonomous Institution “The Department of the State Expertize on the Murmansk region”

• Terms of reference

• Land Selection Act

• Public hearings report

• Technical conditions

• The results of engineering investigations

• The copy of contract with project organization